During project execution, an important stakeholder, who is a capital investor in the client’s business, disagrees with a significant scope item. What should the project manager do ?
A、Advise the stakeholder that it is too late to change the scope
B、Agree to the scope change with the stakeholder
C、Apply the changes management plan for the stakeholder’s scope
D、Terminate the project because the scope is not aligned with the client’s business
10年專注信管,信管教育專注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題