In the last two months of the implementation stage, a software development project has been completed two weeks ahead of schedule. A subject matter expert(SME) gathered some requirements, these requirements are defined to help software end users. Developers expected to demand it, it will also require to verify its availability. Because the develope is ahead of the schedule, what should the project manager do ?
A、Notify the industry experts that the new features are not included in the scope, cannot modify the scope due to non-critical requirements.
B、 Prepare a change request and hand it to the change control board to be considered and approved.
C、 Add the request into the future-improved list, because the change at the end of the project may be at risk.
D、 Demand developing stuffs to execute the change request, because the scope change is expected to take a week, but do not make changes to request.
10年專注信管,信管教育專注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題