試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The overall project plan is developed and approved. The project manager will formally declare the start of the project and present the summary of project milestones schedule to the stakeholders. What will the project manager do next ?
A、Send the project plan to the team members.
B、Schedule a weekly project review meeting.
C、Conduct a team building event.
D、Conduct a kick-off meeting with team members.