Project manager is managing a five months’ project with cost-reimbursable contract and has a total of 500 tasks, of which 100 are completed after two months. All tasks cost and duration are equally dispersed over the months. The following diagram expresses the performance.How many more months would the project manager expect to finish the project?

A、Four months

B、Five months

C、Eight months

D、Ten months