The team members move onto new projects. The project manager moves onto a different project in the organization, White checking the status of the organization’s projects. the project management office notices the contracts for that project were not closed properly. The project manager is asked to correct the issue. Which of the following should the project manager review?
A、Records management system
B、Scope management plan
C、Procurement audits
D、Validate scope