A client requests a scope change request after accepting the design. This change will have a potential impact on several project components. What is the project manager’s MOST APPROPRIATE response?
A、Convince client to delay change
B、Analysis infects of schedule and cost due to the change, and have meeting with team members
C、If this change is critical, then implement it and inform the CCB
D、Estimate the cost and schedule affected by the change, get approval before implement