人人看人人艹,欧美日在线观看,亚洲欧洲在线观看,国内精品视频饥渴少妇在线播放,国产首页,亚洲色图欧美另类,一区二区a视频

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the project ,an incident occurs which impacts the cost of the project, but not the time The event was previously identified as a potential risk by the project team.What should the project manager do to limit the impact of the incident on the project cost?
A、Refer to the risk register to determine the appropriate and agreed upon response
B、Analyze the incident, including impact in cost and time , and create a change request
C、Develop a workaround and implement this immediately to minimize cost overruns
D、Perform a sensitivity analysis to determine the flexibility in cost overruns by different responses


相關(guān)試題

推薦文章