A new project is launched specific software .During the project kick-off meeting, a team member remembers that on a previous project, they had used the first version of that software tool and it led to a multitude of problems.What should the project manager do next?
A、Explain to the team member that technology has changed greatly since the last project .so there will be no issues.
B、Look in the lessons teamed register for the past project to identify similar risks in the new project.
C、Escalate the potential risk immediately to the project sponsor so extra funding can be allocated.
D、Close the project and collect lessons learned, so future projects can benefit from this knowledge.