A project manager is assigned to a multiyear project. During creation of the work breakdown structure(WBS), the project team is unable to decompose some of the phases that will occur during later stages of the project. What should the project manager do?
A、Conduct rolling wave planning when appropriate
B、Return to the requirements gathering stage
C、Estimate WBS decomposition for those phases
D、Reduce the project scope