A company adopted globalization as a risk-mitigation strategy to deal with shrinking growth prospects in developed economies. During the risk review board meeting, the project manager realizes that the company’s global revenues are not growing at the expected rate. Where is the project manager in the project’s life cycle?
A、Risk planning phase
B、Execution of risk response
C、Control risks phase
D、Process of closing risk register